Background
- The case involves a construction lien dispute between Scott Steel Erectors Inc. (subcontractor) and Ausenco Engineering Canada Inc. (contractor) regarding the Magino Gold Mine Project in Northern Ontario.
- Scott Steel and Scott Concrete Services Inc. were separately contracted by Ausenco under three fixed-price subcontracts:
- Building Subcontract (metal buildings for the processing plant)
- SMP Subcontract (structural steel, mechanical, and piping work)
- Concrete Subcontract (concrete work, performed by Scott Concrete)
- On July 25, 2023, Scott Steel registered a $35,250,000 lien, including claims for unpaid amounts and delay damages across all three subcontracts.
Ausenco’s Motion
Ausenco sought to discharge or reduce the lien under the Construction Act, arguing:
- Scott Steel could not lien for the Concrete Subcontract since it was not a party.
- The Building and Concrete Subcontract liens were untimely.
- The lien was exaggerated, particularly regarding delay damages.
Court’s Findings
- Promissory Estoppel May Apply: A triable issue exists regarding whether Scott Steel and Scott Concrete were treated “as one”, potentially allowing Scott Steel to lien for the Concrete Subcontract.
- Exaggerated Delay Damages: The court found no triable issue regarding delay damages for the Building and SMP Subcontracts, as:
- Fixed-price contracts do not normally allow delay claims.
- Scott Steel failed to provide timely notice.
- Claimed damages varied significantly without sufficient documentation.
- Lien Reduced: The court reduced the lien to $26,747,526.53, allowing delay damages only under the Concrete Subcontract.
- Costs deferred to the trial judge?.
Partial success for both parties:
- Ausenco succeeded in reducing the lien due to exaggerated claims.
- Scott Steel succeeded in maintaining the lien (albeit at a reduced amount) and establishing a triable issue on promissory estoppel regarding the Concrete Subcontract.