2238649 Alberta Ltd. v Graham Carillion NBJV
2238649 Alberta Ltd.
101200672 Saskatchewan Ltd.
Graham Carillion NBJV
Law Firm / Organization
MLT Aikins LLP
Access Prairies Holding Inc.
Law Firm / Organization
MLT Aikins LLP
Access Prairies LP
Law Firm / Organization
MLT Aikins LLP
Access Prairies Partnership
Law Firm / Organization
MLT Aikins LLP
Graham APP Holdings Ltd.
Law Firm / Organization
MLT Aikins LLP
Graham APP GP Beta Holdings Ltd.
Law Firm / Organization
MLT Aikins LLP
Graham Design Builders LP
Law Firm / Organization
MLT Aikins LLP
Graham Design Builders Ltd.
Law Firm / Organization
MLT Aikins LLP
Carillion Canada Inc.
Law Firm / Organization
Unrepresented
Gracorp Capital Advisors LP
Law Firm / Organization
MLT Aikins LLP
Carillion Private Financial Ltd.
Law Firm / Organization
Unrepresented
Kasian Architecture Interior Design and Planning Ltd.
Law Firm / Organization
McDougall Gauley LLP
WSP Canada Inc.
Law Firm / Organization
Unrepresented
Delco Automation Inc.
Saskatchewan Health Authority
Law Firm / Organization
Unrepresented
Government of Saskatchewan
Law Firm / Organization
Unrepresented
Graham Construction and Engineering LP
Law Firm / Organization
MLT Aikins LLP
Graham Construction and Engineering Inc.
Law Firm / Organization
MLT Aikins LLP
University of Saskatchewan
Law Firm / Organization
McKercher LLP
John Doe I
Law Firm / Organization
Unrepresented
John Doe II
Law Firm / Organization
Unrepresented
John Doe III
Law Firm / Organization
Unrepresented
John Doe IV
Law Firm / Organization
Unrepresented
John Doe V
Law Firm / Organization
Unrepresented

Background:
2238649 Alberta Ltd. and 101200672 Saskatchewan Ltd. sued Graham Carillion NBJV and related entities over a multi-million-dollar construction dispute regarding the North Battleford Project in Saskatchewan. The claims involved breach of contract, unpaid invoices, and change orders totaling $9.7 million, a $14 million delay claim, and a $20 million unjust enrichment claim. Additional disputes arose over electrical work at the University of Saskatchewan.

Legal Issues:

  1. Failure to Post Security for Costs – The plaintiffs failed to comply with security for costs orders issued in August 2022, leading Graham Carillion NBJV and Graham Construction to apply for dismissal.
  2. Limitations Period – Graham Carillion NBJV argued the claims were statute-barred under The Limitations Act, as they were discoverable by December 2017 but not filed until January 2020.
  3. Lack of Authority to Sue – The plaintiffs commenced the actions while 101200672 Saskatchewan Ltd. was in receivership, without court authorization.
  4. Arbitration Clause – The subcontract required disputes to proceed by arbitration, which the plaintiffs ignored.

Outcome and Costs:
The court dismissed all four claims for non-compliance with security for costs and struck them as an abuse of process. Graham Carillion NBJV and Graham Construction were awarded $2,500 each in application costs and full costs on Column 3 of the Tariff of Costs for the dismissed actions.

Court of King's Bench for Saskatchewan
QBG-RG-00142-2020
Construction law
Defendant