Facts:
Brillion Homes, owned by Mr. Nguyen, hired Tony Hayre Management Services Ltd. to manage the completion of a commercial/residential property. The contract was disputed—Mr. Hayre claimed it was a monthly service agreement until project completion, while Mr. Nguyen argued it was for a fixed amount to be completed in 12 months.
Legal Issues:
Result:
The court ruled in favor of Tony Hayre Management Services Ltd., awarding it $30,000 (two months' fees at $15,000 per month) plus an additional $6,666.67 (for post-project fees), along with prejudgment interest and GST. A claim for $2,250.04 for unspecified labor was dismissed. The total award, excluding interest and costs, was $36,666.67.
Court
Supreme Court of British ColumbiaCase Number
S235464Practice Area
Construction lawAmount
$ 36,667Winner
PlaintiffTrial Start Date