Twister Developments Ltd v 1406676 Alberta Ltd
Twister Developments Ltd.
Law Firm / Organization
Stephens Mah Toogood (SMT Legal)
Lawyer(s)

Roger C. Stephens

1406676 Alberta Ltd.
Law Firm / Organization
McLennan Ross LLP

Case Background

  • In 2014, Twister Developments Ltd. ("Twister") and 1406676 Alberta Ltd. ("140") entered into an agreement to construct two commercial buildings in Fort McMurray.
  • Twister began construction, but the relationship was terminated by 140 in July 2016, before the project was completed.

Key Issues:

  1. Contract Dispute:
    • The court found the relationship was governed by a cost-plus contract, despite signed fixed-price contracts. These contracts were created to secure bank financing and did not reflect the actual agreement.
  2. Payment Owed to Twister:
    • Twister was found to be owed $173,012.08 for completed work. The invoices were cleared through a quantity surveyor and approved by the bank before payment.
  3. 140's Claims Against Twister:
    • Overpayment: The court rejected 140’s argument that it overpaid Twister, finding no basis for overpayment under the cost-plus arrangement.
    • Delays and Lost Rental Revenues: Delays were caused by unforeseeable issues, including permit requirements and a major fire in Fort McMurray. Twister was not held responsible for these delays or lost rental revenues.
    • Deficiencies in Work: Twister was not given a reasonable opportunity to rectify any deficiencies before being removed, so 140 could not claim repair costs.

Conclusion:

  • Judgment: 140 must pay Twister $173,012.08. No further payments are owed by Twister for alleged deficiencies, delays, or overpayment claims.
Court of King's Bench of Alberta
1703 10277
Construction law
$ 173,012
Plaintiff