29 Jul 2024
Nature Ridge Homes Ltd. v. Faulkner
Background:
- Agreement: The Faulkners contracted Nature Ridge Homes Ltd. to build a house in Porter’s Lake for $599,000.
- Issue: Rising lumber costs led to disputes over increased construction costs.
- Small Claims Court: Ruled that the Faulkners overpaid due to duress, ordering repayment of certain overages.
- Appeal: Nature Ridge Homes Ltd. appealed the decision.
Key Findings and Reasoning:
- Initial Contract:
- Date: February 5, 2021.
- Terms: Included provisions for cost overages but did not specify handling unforeseen inflation.
- Cost Overages:
- Communication: The Faulkners were notified about potential lumber cost increases in April 2021.
- Response: Faulkners chose to proceed with the additional costs rather than cancel the contract.
- Adjudicator’s Decision:
- Findings: The increased costs were included in a later Schedule “E”, which the Faulkners signed under pressure due to lack of alternatives.
- Conclusion: Found economic duress, ordered repayment of specific overages.
- Grounds for Appeal:
- Economic Duress: Claimed it was applied incorrectly as a cause of action rather than a defense.
- Contract Interpretation: Asserted that the original contract did not authorize additional charges for lumber without consent.
- Supreme Court Decision:
- Error in Law: Found the Adjudicator misapplied evidence and legal principles.
- No Choice: Determined the Faulkners had alternatives and had agreed to additional costs previously.
- Contract Terms: Noted original awareness of rising costs, invalidating duress claim.
Outcome:
- Appeal Allowed: The Adjudicator’s decision was quashed.
- Order: Monies paid to the Faulkners to be returned, and the Appellant awarded costs. Excat total amount awarded was not specified.