Vertical Horizons Contracting Inc. v. Markham (City)
Vertical Horizons Contracting Inc.
Law Firm / Organization
Klug Law
Lawyer(s)

Leo Klug

The Corporation of the City of Markham
Law Firm / Organization
Scalisi Barristers

Case Background

  • Contract: Replacement of a sanitary sewer system (165 meters of pipe).
  • Dispute: Issues with water presence and soil nature led to additional expenses for the appellant.
  • Action Taken: The respondent terminated the contract, hired another company to complete the work, and counterclaimed for damages.
  • Trial Court Decision: Appellant breached the contract but was owed some amounts for completed work. Net amount owed by the appellant to the respondent after set-off: $22,291.25 (Superior Court of Justice, Justice Phillip Sutherland, 2023 ONSC 113).

Appeal Decision

  • Appeal: Vertical Horizons Contracting Inc. appealed the trial court's judgment.
  • Appellant's Argument: Challenged the finding of contractual breach and interpretation of the contract.
  • Court of Appeal Findings:
    • No palpable and overriding error in the trial judge's factual findings.
    • No reversible error in the contract interpretation.
    • Appellant was responsible for the methodology and subsequent impacts despite initial excusal for the first 30 meters.
  • Outcome: Appeal dismissed.
  • Costs: Respondent awarded $20,000 inclusive of disbursements and HST.

Key Points

  • The appellate court emphasized reliance on trial evidence and factual findings.
  • The contract held the appellant responsible for the chosen methodology and its consequences.
  • The appeal failed to establish any significant errors warranting reversal of the trial decision.

Summary of Total Monetary Amounts

  • Total Damages: $22,291.25
  • Costs of Appeal: $20,000
  • Grand Total: $42,291.25

 

Court of Appeal for Ontario
COA-23-CV-0187
Civil litigation
$ 42,291
Respondent