Knox Presbyterian Church v. Oakwood Designers & Builders
THE TRUSTEES OF THE KNOX PRESBYTERIAN CHURCH MANOTICK
Law Firm / Organization
Soloway Wright LLP
Lawyer(s)

Daniel J. Leduc

OAKWOOD DESIGNERS & BUILDERS INC.
Law Firm / Organization
Vincent Dagenais Gibson LLP/s.r.l.
Lawyer(s)

Melanie Levesque

Background:

  • In 2018 and 2019, Knox Presbyterian Church and Oakwood entered into agreements for a wheelchair-accessible addition.
  • Agreements:
    • 2018: Intent agreement for design and scope.
    • 2019: Two contracts—Oakwood General Construction Contract (Construction Contract) and CCDC14 Design-Build Stipulated Price Contract (CCDC Contract) for $774,500.
  • Dispute arose when work paused due to a buried Hydro One power line, resuming with Oakwood demanding a price increase.

Key Issues:

  1. Which dispute resolution method applies?
  2. Is the application stayed pending service on Hydro One?
  3. Are the parties required to arbitrate?

Findings:

  • Dispute Resolution:
    • Court's Decision: GC 8.1 of the CCDC Contract applies (negotiation, mediation, arbitration), not Section 36 of the Construction Contract.
  • Hydro One's Role:
    • Decision: Arbitrator will decide if Hydro One is necessary.
  • Referral to Arbitration:
    • Order: Parties must arbitrate. Gerald Genge is the arbitrator unless agreed otherwise.

Disposition:

  • Application granted; respondent’s motion dismissed.
  • Costs to be resolved by June 24, 2024, or decided by the court based on cost outlines. No amount specified.

Key Points:

  • Arbitration Clause: Prevails over court adjudication per CCDC Contract.
  • Competence-Competence Principle: Arbitration process prioritized for jurisdictional questions.
  • Hydro One's Involvement: Arbitrator’s decision, not a precondition for arbitration.
Superior Court of Justice - Ontario
CV-23-92186
Civil litigation
Applicant