In 2018 and 2019, Knox Presbyterian Church and Oakwood entered into agreements for a wheelchair-accessible addition.
Agreements:
2018: Intent agreement for design and scope.
2019: Two contracts—Oakwood General Construction Contract (Construction Contract) and CCDC14 Design-Build Stipulated Price Contract (CCDC Contract) for $774,500.
Dispute arose when work paused due to a buried Hydro One power line, resuming with Oakwood demanding a price increase.
Key Issues:
Which dispute resolution method applies?
Is the application stayed pending service on Hydro One?
Are the parties required to arbitrate?
Findings:
Dispute Resolution:
Court's Decision: GC 8.1 of the CCDC Contract applies (negotiation, mediation, arbitration), not Section 36 of the Construction Contract.
Hydro One's Role:
Decision: Arbitrator will decide if Hydro One is necessary.
Referral to Arbitration:
Order: Parties must arbitrate. Gerald Genge is the arbitrator unless agreed otherwise.