Monalt Environmental Inc. v. BDA Inc.
MONALT ENVIRONMENTAL INC.
Law Firm / Organization
Drudi, Alexiou, Kuchar LLP
Lawyer(s)

Robert Kalanda

YORK UNIVERSITY
Law Firm / Organization
Not Specified
Lawyer(s)

D. Goodman

BDA INC.
Law Firm / Organization
Not Specified
Lawyer(s)

D. Goodman

Summary:

  • Monalt Environmental Inc. (Plaintiff) was subcontracted by BDA Inc. (Defendant) for asbestos abatement and demolition at York University's Glendon Campus.
  • The dispute centered on whether Monalt’s scope of work included certain demolition tasks, leading to non-payment by BDA and a subsequent construction lien by Monalt.
  • The court found that Monalt's scope included the disputed work, and their failure to complete it constituted a breach of contract.

Key Points:

  • Monalt argued that its contract was limited to specific tasks outlined in their quotes, whereas BDA contended that Monalt agreed to a broader scope of work.
  • The court decided that Monalt was contractually obligated to complete the disputed demolition work, based on the comprehensive language of the contract and the conduct of the parties.
  • BDA was justified in withholding payment due to Monalt’s incomplete work, and Monalt’s suspension of work was seen as a repudiation of the contract.
  • Monalt's lien was discharged, and the court directed the lien bond posted by Monalt to be returned to BDA.

Outcome:

  • Monalt’s action for the claim and BDA’s counterclaim were dismissed, with the court finding that both parties had a measure of divided success.
  • BDA was awarded costs of $20,000 inclusive of all taxes and disbursements, to be paid by Monalt.
Superior Court of Justice - Ontario
CV-20-650113
Construction law
$ 20,000
Defendant