Marrbeck was contracted by WCC 40 for building envelope remediation and subcontracted Transcona for roofing work.
Disputes arose over unpaid invoices and alleged work deficiencies.
Marrbeck sought summary judgment for $1,272,917.20, while Transcona claimed $1,184,388.01.
Claims:
Transcona: Sought payment for unpaid invoices and work performed.
Marrbeck: Claimed certified payment and additional work costs.
Defenses:
WCC 40: Argued the work was deficient and inappropriate for summary judgment due to conflicting expert evidence.
Rulings:
Summary Judgment: The court found the case suitable for summary judgment, favoring CKP's project assessment over other expert opinions.
Payment: Marrbeck and Transcona were deemed to have performed the work. CKP’s certifications were binding, and WCC 40 failed to use the contract’s dispute resolution mechanism.