Background
- Project: Condominium construction at 200 Woodbine Ave., Toronto.
- Parties:
- LMB: Trade contractor for plumbing, gas, and HVAC work.
- 200: Property owner and developer.
- Dispute:
- LMB claimed unpaid amounts, including extras due to design changes.
- 200 argued LMB was overpaid and asserted set-offs for incomplete/deficient work.
- LMB registered a lien for $260,134.31, later reduced to $244,611.49.
Court Findings
-
Base Contract Work:
- LMB’s work was substantially complete except for fixtures in two penthouse units.
- Court adjusted the claim, valuing LMB’s completed contract work at $1,530,450.
-
Extras & Changes:
- LMB claimed 232 change invoices; 165 were paid, 67 were not.
- Court ruled 200 waived strict contract compliance by paying most change invoices.
- The 165 paid extras were valid, but LMB failed to prove entitlement to the unpaid 67.
-
Lien Timeliness & Abandonment:
- LMB abandoned the contract before registering its lien, exceeding the 45-day limit.
- Lien declared expired, and lien bond returned to 200.
-
Breach of Contract:
- LMB breached by wrongfully suspending work, but still earned compensation.
-
Deficiencies & Set-Offs:
- 200 failed to prove deficiencies or damages, and its counterclaim was dismissed.
Final Judgment
- LMB awarded $172,740.47 for unpaid work.
- Lien expired; 200 entitled to lien bond return.
- 200’s counterclaim dismissed.